Sun asked to sign provisional agreement and commence signals to MSO

Sun asked to sign provisional agreement and commence signals to MSO

INB

New Delhi: Sun Network has been directed by the Telecom Disputes Settlement and Appellate Tribunal to enter into a provisional interconnect agreement with multi system operator Balu Cable Network and commence supply of signals.

 

Chairman Justice Aftab Alam and member Kuldip Singh felt that the order was proper and appropriate considering much time has already lapsed.

 

The Tribunal said: “We note that this petition was filed on 28 May 2015 and it is lingering on, on some pretext or the other. The request on behalf of the respondent for making physical verification of the petitioner’s SLR cannot be disallowed.”  

 

Listing the matter for 14 December, the Tribunal said Sun Network may make a physical verification of the petitioner’s SLR and submit its report on completion of the verification.

 

Thereafter, the Tribunal will pass further orders, the bench said.